Major Works Undertaken (Status as on 30.06.2020)
S. No. | Name of Project | Assignment to SNPL | Client | Current Status |
1. | Sawalkot Hydroelectric Project (1856 MW) in Jammu and Kashmir | Development of Construction Methodology and Review of Costs for DPR. | DMR Hydro Engineers P. L. Faridabad Prime Assigner: Hindustan Construction Co., Mumbai | Commenced on: March 2013 Submitted on: June 2013 DPR Submitted to CWC. Reviews in Progress. |
2. | Ubharah Small Hydroelectric Project (2.4 MW) in Chuwari, Chamba, HP | Project Management- Construction Supervision, Quality Control, Contracts and Billing, Management, Procurement of Major Construction material and equipment. | Shakti Hydro Project Limited | Commenced on: April 2013 The Project completed and commissioned on 18th Nov. 2014. Design of additional water conducting system completed I March 2017. Construction in progress. |
3. | Katende Hydroelectric Project (60 MW) | Project Planning -Development of construction methodology, Equipment Planning, Manpower Planning | Tractebel Engineering Pvt. Ltd. Delhi | Commenced: April 2013 Submitted: June 2013 |
4. | Chachyote Small Hydroelectric Project (3.5 MW) in Mandi, HP | Project Management- Complete Construction management, Design, Quality Control, Contracts, Management, | Shakti Hydro Project Limited, Delhi | Commenced: October 2014 Detailed survey and final layout Design of the Project completed. Detailed design in Progress. Construction likely to be taken up by April 2018. |
5. | Karnah Hydroelectric Project (12 MW) in J&K | Development of EPC Contract Documents and support in tendering process –Our scope limited to civil works portion only. | Synergics India PrivateLimited. Noida | Commenced: October 2014 Submitted: December 2014; Reviews up to July 2017 Tenders floated in July 2017. Pre bid queries responded. |
6. | Chavuma Small Hydroelectric Project (14 MW) in Zambia | Project Review and assessment for Bidding on BOO Basis | SIC P. L. Zambia | Commenced: February 2014 Report Submitted: February 2014 |
7. | Tamu Hydro Electric Project in Myanmar | Project Appraisal and Development of Construction Methodology. | Sharp Engineering P. L. Faridabad | Commenced: November 2014 Report Submitted:January 2014 |
8. | North Yammar Hydro Electric Project Stage-II (2.4 MW capacity enhancement) in Myanmar | Project Appraisal and Development of Construction Methodology, Design support. | Sharp Engineering P. L. Faridabad | Completed and submitted to the Client. |
9. | Dugar Hydroelectric Project (421 MW)in Himachal Pradesh | Development of Infrastructure Planning and Construction Methodology, Construction Schedule and Design Support. | Consultant: AF Consult, Noida Owner: Dugar Hydro Power Limited | Commenced in July 2014 Submitted:September 2014 DPR Submitted in August 2015. |
10. | Lower Kalnai Hydroelectric Project (45 MW)in Jammu and Kashmir. | Development of Infrastructure Planning, Construction Scheduleand Design Support. | Consultant: AF Consult EPC Contractor: Coastal Projects Limited Owner: JKSPDC, J&K | Commenced in July 2014 Submitted: September 2014 Finalized in November 2014. |
11. | Kutehr Hydroelectric Project (240 MW)in J&K | Development of EPC Contract Documents and support in tendering process | Main Consultant: Entura Hydro Tasmania Owner: JSW (Jindal Steel Works} | Commenced: November 2014 Submitted :November 2014 RFP (Request for Proposal Issued in January 2015. Pre-bid procedures and Bid evaluation completed. |
12. | Luj Small Hydroelectric Project | Preparation of Detailed Project Report, Excluding, Survey and Investigations and Geology and Hydrology. | Consultant: AF Consult Owner: Dugar Hydro Power Limited | PFR Submitted to Him Urja. DPR under Preparation. |
13. | Water Treatment Plant and Pumping Station (14 MLD) at Shapur Kandi HEP. | Conceptual Design of 14 MLD Water Treatment Plant and Pumping Station. | PHE, Punjab | Completed |
14. | Upper Karnali Hydroelectric Project (900 MW), Nepal | Review of design and drawings, Development of Construction Methodology, quantities calculations for revised drawingsand Review of Costs. | GMR Upper Karnali Hydro Power Limited. | Construction Methodology and Complete costing submitted. Under review by the client. |
15. | Augmentation of LWSS Water Supply Scheme, Chail, Mandi, HP | Structural Design of Water Tanks | I&PH, Gohar, Himachal Pradesh | Completed. |
16. | 14 numbers of 132/33/11 kV Substation in Bihar | Project Management and Construction Supervision | Skipper SEIL (India) Pvt. Ltd. Gurgaon. | Started from December 2015. Term 6 Months. Erection, testing and commissioning (Successfully Charging Charging) 4 Nos. of 50 MVA Transformers and a number of 132/33 bays. Work was in Progress. Withdrawn by SNPLin May 2016 due to payment related and other issues. |
17. | Phulibagar and Burthing Hydroelectric Project (Two projects) | Preparation of General Draft Tender Documents | Essel Infraprojects Private Limited. | Started from May 2016. Work Completed and submitted and accepted by the client. |
18. | Konda Hydroelectric Project | Development of Construction Methodology,quantities calculations and Costing for Tendering. | DMR Hydro Engineers P. L. Faridabad Prime Assigner :KRK Infracon, Hyderabad | Started from October 2016. Work Completed and tender submitted. |
19. | Modification and Strengthening of Existing Cargo Berths No. 1 To 6 At Kandla | Preparation of Claim Documents | Bumi Geo Engineering Ltd. | Documentation Complete. Arbitration Proceedings in Progress. |
20. | Providing and laying Trunk Sewer line in colonies of the Constituency: Part of Gokulpur and Part of Karawal Nagar falling under Yamuna Vihar WWTP Catchment area through Trenchless Technology in Delhi | Preparation of Tender Documents and support services. | Bumi Geo Engineering Ltd. | Documentation Complete. Tender Submitted. |
21. | Single Line BG Tunnel 12 from Km 63.626 To Km 68.320 In between Khongsang – Tupul | Preparation of Claim Documents | Coastal Projects Limited. | Dec.’17 to Feb.’17 Draft Documentation Complete. Reviewed by Coastal completed. |
22. | Bangalore Water Supply and Sewerage Project (II) Contract S1d – Sewage Treatment Plant (90 mld) at Bellandur Amanikere, Bangaluru | Quantity Survey and Project Scheduling and Monitoring | VA Tech WABAG | Commenced in July 2017; on going |
23. | Sewage Treatment Plant and Pumping Stations In Odisha(48 mld) Bhubneshwar Sewrage District –VI | Quantity Survey and Project Scheduling and Monitoring | VA Tech WABAG | Commenced in July 2017; on going |
24. | Boali – 2 HEPs Project 12 MW Augmentation) Boali,Province Ombella-M’poko, Central African Republic (CAR) | Development of Construction Methodology, quantities calculations and Costing for Tendering | Prime Assigner: ENERGIE CENTRAFRICAINE | Started from October 2017. Work Completed and tender submitted. |
25. | Effluent Treatment Plant –C2 ETP Complex, Reliance Programme 3,Jamnagar | Quantity Survey for final quantity calculations and verifying the contractors Bills and Payments, reconciliation of quantities paid and actual, analysing time and cost variation. | VA Tech WABAG | Commenced in December 2017; Final Report submitted on 26th March 2018. |
26. | Preparation of Dam Safety Guidelines for Laos PDR | Preparation of Dam Safety Guidelines for Laos PDR | Entura Hydro Tasmania | Major works completed. Review by World Bank team and Others in progress. All major clarifications provided. Almost in final stage. |
27. | Teesta HE Project Phase – VI | Costing for Tender | DMR Hydro for Statkraft, Norway | Completed and submitted to the Client for consideration in Bid. |
28. | Improvement and widening to fourlane with paved shoulder of Manu – Simlung section of NH-44A in the state of Tripura on EPC mode – package – III starting near Kanchanpur at km 46.597 and ending near Vaghmun at km 66.845 | Costing for Tender | Vensar Construction Co. Ltd., Hyderabad | Completed and submitted to the Client for consideration in Bid in January 2019. |
29. | Improvement & wideningof Kailashahar-Teliamura section of NH-208 package-VI from km 105.300(designchainage 97.319) to km 139.453 (design chainage 127.319)in Tripura | Costing for Tender | Vensar Construction Co. Ltd., Hyderabad | Completed and submitted to the Client for consideration in Bid in January 2019. |
30. | Kholongchhu Hydroelectric Project (600 mw), Trashiyangtse, Bhutan, Package: KC – 1 Construction of river diversion works, dam intake,DesiltingArrangementand HRT from RD0.00 m to RD 2,303.00 m including construction adits. | Construction Planning, Scheduling, Methodology and Costing for tender/ bid | Energy Infratech Pvt. Ltd., Noida | Completed and submitted to the Client for consideration in Bid in March 2019. |
31. | Kholongchhu Hydroelectric Project (600 mw): Package: KC – 2: Construction of Head Race Tunnel from RD 2303.00 m to RD 14091.07 m including construction adits II, III, IV, V and Chaplangchu Diversion Works | Construction Planning, Scheduling, Methodology and Costing for tender/ bid | Energy Infratech Pvt. Ltd., Noida | Completed and submitted to the Client for consideration in Bid in March 2019. |
32. | Kholongchhu Hydroelectric Project (600 Mw): Package: KC – 3: Construction of Head Race Tunnel from RD 14,091.07 m to RD 15762.80 m including construction adit VI Surge Shafts, Butterfly Valve Chamber, Pressure Shafts, Powerhouse Complex and Tail Race Tunnel | Construction Planning, Scheduling, Methodology and Costing for tender/ bid | Energy Infratech Pvt. Ltd., Noida | Completed and submitted to the Client for consideration in Bid in May 2019. |
33. | Kutehr Hydroelectric Project (240 Mw): Himachal Pradesh, India: Package JSWEKL/Lot-2: Civil Works for Remaining Part of Headrace Tunnel (From Rd7500 m TO RD 14750 m), Surge Shaft, Pressure Shaft, Steel Liner, Underground Powerhouse, Underground Transformer Hall, Collection Gallery, Tailrace Tunnel and Pot Head Yard including Approach Roads & Dump Yards | Construction Planning, Scheduling, Methodology and Costing for tender/ bid. | MF Bumi Geotech Private Limited | Completed and submitted to the Client for consideration in Bid in June 2019. |
34. | Stabilization of Slopes at Nirgad near Rishikesh, Jawadi near Rudraprayag and Padli near Nainital Under Project for Natural Disaster Management in Forest Areas in Uttarakhand | Development of Construction Schedule, Construction Methodology, QA&QC Plan, and HSE Plan | MF Bumi Geotech Private Limited | Completed and submitted to the Client for consideration in Bid in July 2019. |
35. | Lower Hewakhola Hydroelectric Project, Nepal. | Preparation of response to arbitration claims and counter claims | Mountain Hydro Nepal Ltd. | July August 2019 |
36. | Kutehr Hydroelectric Project (240 Mw): Himachal Pradesh, India: Package JSWEKL/Lot-2 (Described above) | Review of Construction, Schedules, Equipment Planning, Manpower Planning and technical and commercial discussions with Suppliers. | MF Bumi Geotech Private Limited | On going |
37. | Bajoli Holi Hydroelectric Project 180 MW, | Due diligence on Technical aspects of construction and quality and balance costs for taking stakes in the Project. | STATKRAFT India Pvt. Ltd. | Completed in Dec. 2019 |
38. | Design and construction of Broad Gauge Ballast-Less Track under Contract Package 1 of 4 for Tunnel No.1 to 6, Contract Package 2 of 4 for Tunnel No. 6 to 11C and Contract Package 3 of 4 for Tunnel No. 12 to 18 and all other ancillary work in connection with construction of New BG Line in between Jiribam to Imphal. | Preparation of Claims against Expenses and losses suffered due to delays and incompletion of Works. | Royal-CPL JV A JV of Royal Infraconstru Limitedand Coastal Projects Limited. & | Completed January 2020. |